Airport Taxilane construction Project
Belle Fourche Airport Hangar Taxilane Project Schedule
| No. |
Start Date |
End Date |
Task |
| 1 | 6/15/2026 |
6/20/2026 |
Mobilization/ Staging Area Prep |
| 2 | 6/22/2026 |
6/24/2026 |
Construct Temporary Access Route |
| 3 | 6/24/2026 |
6/26/2026 |
Phase 1 Demolition |
| 4 | 6/29/2026 |
7/2/2026 |
Excavation For Phase 1 |
| 5 | 7/6/2026 |
7/8/2026 |
Final Grading of Phase 1 |
| 6 | 7/8/2026 |
7/10/2026 |
Phase 2 Demolition |
| 7 | 7/13/2026 |
7/17/2026 |
Excavation For Phase 2 |
| 8 | 7/20/2026 |
7/22/2026 |
Final Grading of Phase 2 |
| 9 | 7/22/2026 |
7/24/2026 |
Phase 3 Demolition |
*17 step project projected to be completed by 9-5-26
ROGERS CONSTRUCTION, INC.
(605) 722-4080
rogersconstruction2@rushmore.com
722 14th St., Sturgis, SD 57785