Airport Taxilane construction Project

Belle Fourche Airport Hangar Taxilane Project Schedule

 

No.
Start Date
End Date
Task
1-5 6/15/2026
COMPLETED
Mobilization/ Staging Area Prep
Construct Temporary Access Route
Phase 1 Demolition
Excavation For Phase 1
Final Grading of Phase 1
6 7/8/2026
7/10/2026
Phase 2 Demolition
7 7/13/2026
7/17/2026
Excavation For Phase 2
8 7/20/2026
7/22/2026
Final Grading of Phase 2
9 7/22/2026
7/24/2026
Phase 3 Demolition
10 7/27/2026     7/31/2026 Excavation For Phase 3
11 8/3/2026 8/5/2026 Final Grading of Phase 3
12 8/5/2026     8/7/2026     Remove Temporary Access Route
13 8/10/20    26 8/12/2026 Phase 4 Demolition

*17 step project projected to be completed by 9-5-26

ROGERS CONSTRUCTION, INC.

(605) 722-4080

rogersconstruction2@rushmore.com

722 14th St., Sturgis, SD 57785