CONSTRUCTION_SAFETY_PHASING_PLAN_-_PHASE_1_(002)

Airport Taxilane construction Project

Belle Fourche Airport Hangar Taxilane Project Schedule

 

No.
Start Date
End Date
Task
1 6/15/2026
6/20/2026
Mobilization/ Staging Area Prep
2 6/22/2026
6/24/2026
Construct Temporary Access Route
3 6/24/2026
6/26/2026
Phase 1 Demolition
4 6/29/2026
7/2/2026
Excavation For Phase 1
5 7/6/2026
7/8/2026
Final Grading of Phase 1
6 7/8/2026
7/10/2026
Phase 2 Demolition
7 7/13/2026
7/17/2026
Excavation For Phase 2
8 7/20/2026
7/22/2026
Final Grading of Phase 2
9 7/22/2026
7/24/2026
Phase 3 Demolition

*17 step project projected to be completed by 9-5-26

ROGERS CONSTRUCTION, INC.

(605) 722-4080

rogersconstruction2@rushmore.com