Airport Taxilane construction Project
Belle Fourche Airport Hangar Taxilane Project Schedule
| No. |
Start Date |
End Date |
Task |
| 1-5 | 6/15/2026 |
COMPLETED |
Mobilization/ Staging Area Prep Construct Temporary Access Route Phase 1 Demolition Excavation For Phase 1 Final Grading of Phase 1 |
| 6 | 7/8/2026 |
7/10/2026 |
Phase 2 Demolition |
| 7 | 7/13/2026 |
7/17/2026 |
Excavation For Phase 2 |
| 8 | 7/20/2026 |
7/22/2026 |
Final Grading of Phase 2 |
| 9 | 7/22/2026 |
7/24/2026 |
Phase 3 Demolition |
| 10 | 7/27/2026 | 7/31/2026 | Excavation For Phase 3 |
| 11 | 8/3/2026 | 8/5/2026 | Final Grading of Phase 3 |
| 12 | 8/5/2026 | 8/7/2026 | Remove Temporary Access Route |
| 13 | 8/10/20 26 | 8/12/2026 | Phase 4 Demolition |
*17 step project projected to be completed by 9-5-26